Regarding the case that the branch office is handling the “Kaohsiung Port Container Terminals 3 & 5 Reconstruction Project” Part II (Pier 70 Deepening Reconstruction Project) dredging and backfilling and pier side scouring excavation and rock throwing operations. Please inform your affiliated members or vessels to exercise caution and give way when navigating through this area for navigation safety.

:::
2025-04-09 Kaohsiung
Harbor No. 1146590818
Explanation:
1. According to our branch's letter No. 1146206099 dated March 31, 2025.
2. Work period: From April 1, 2025 to May 15, 2025.
3. Operating vessels: Kuntoku No.2.
4. Contact persons and phone numbers are as follows:
(1) Construction company: One Mountain Construction Co., Ltd. Public Works Office Tel: 07-8214813, Site Director Liu Lian-Fu 0929-422-050.
(2) Supervision company: Yutai Engineering Consultants Ltd. - Mr. Li Jiyu (0933-054625).
(3) Our company: Engineer Su Xiu-hong 07-5622669.
5. A copy of the "Construction Area Map" is attached for your reference.
Attachment download
File Name File format
Construction Area Map Hash Value File format:PDF
File format:PDF File Size:683 KB Download Counter:0
Last Updated:2025-04-09