Notice Regarding Caisson Fabrication, Towing, and Positioning Operations for the "Outer Breakwater Construction" under the "Kaohsiung Port Intercontinental LNG Terminal Construction Project" Organized

:::
Ref No: Harbor No. 1156591216
Explanation:
1. This work is conducted in accordance with our branch office’s official letter No. 1156207332, dated April 27, 2026.
2. Operation Period: From April 27, 2026, to September 28, 2030.
3. Working Vessels: A total of 29 vessels, including Hung Hua.
4. Contact Persons and Phone Numbers:
(1) Contractor: Hung Hua Construction Co., Ltd. – Tel: 07-8711188.
(2) Supervisors: CECI Engineering Consultants, Inc., Taiwan – Tel: 07-8716368.
(3) Our Branch Office: Engineer Liao Wen-Cheng – Tel: 07-5622674.
5. Attached herewith is one copy of the "Construction Area Map and Contact List."
Attachment download
File Name File format
Notice Regarding Caisson Fabrication, Towing, and Positioning Operations for the "Outer Breakwater Construction" under the "Kaohsiung Port Intercontinental LNG Terminal Construction Project" Organized Hash Value File format:PDF
File format:PDF File Size:1 MB Download Counter:1
Last Updated:2026-05-08
Top